Charms upgrade¶
The Juju command to use is upgrade-charm. For extra guidance see How to upgrade applications in the Juju documentation.
Please read the following before continuing:
Note
A charm upgrade affects all corresponding units; upgrading on a per-unit basis is not currently supported.
Upgrade order¶
There is no special order in which to upgrade the charms. The order described here is based on the upgrade order for OpenStack upgrades, which, in turn, is the order used by internal testing.
Caution
Although it may be possible to upgrade some charms concurrently (i.e. in parallel), it is not recommended. Charm upgrades should be performed sequentially (i.e. one at a time). Also, verify that a charm upgrade has succeeded before moving on to the next.
The general order is:
all principal charms
all subordinate charms
The precise order within the group of principal charms is shown in the below table.
Note
Only stable charms are listed in the upgrade order table.
Order |
Charm |
---|---|
1 |
|
2 |
|
3 |
|
4 |
|
5 |
|
6 |
|
7 |
|
8 |
|
9 |
|
10 |
|
11 |
|
12 |
|
13 |
|
14 |
|
15 |
|
16 |
|
17 |
|
18 |
|
19 |
|
20 |
|
21 |
|
22 |
|
23 |
|
24 |
|
25 |
|
26 |
|
27 |
|
28 |
Upgrade testing for subordinate charms does not follow a prescribed order. Once all the principal charms have been processed all the subordinate charms can then be upgraded in any order.
Perform the upgrade¶
Prior to upgrading a charm, say keystone, a (partial) output to juju status may look like:
App Version Status Scale Charm Store Rev OS Notes
keystone 15.0.0 active 1 keystone jujucharms 306 ubuntu
Unit Workload Agent Machine Public address Ports Message
keystone/0* active idle 3/lxd/1 10.248.64.69 5000/tcp Unit is ready
Here, as deduced from the Keystone service version of ‘15.0.0’, the cloud is running Stein. The ‘keystone’ charm however shows a revision number of ‘306’. Upon charm upgrade, the service version will remain unchanged but the charm revision is expected to increase in number.
So to upgrade the keystone charm:
juju upgrade-charm keystone
The upgrade progress can be monitored via juju status. Any encountered problem will surface as a message in its output. This sample (partial) output reflects a successful upgrade:
App Version Status Scale Charm Store Rev OS Notes
keystone 15.0.0 active 1 keystone jujucharms 309 ubuntu
Unit Workload Agent Machine Public address Ports Message
keystone/0* active idle 3/lxd/1 10.248.64.69 5000/tcp Unit is ready
This shows that the charm now has a revision number of ‘309’ but Keystone itself remains at ‘15.0.0’.
Caution
Any software changes that may have (exceptionally) been made to a charm currently running on a unit will be overwritten by the target charm during the upgrade.
Upgrade target revisions¶
By default the upgrade-charm command will upgrade a charm to its
latest stable revision (a possible multi-step upgrade). This means that
intervening revisions can be conveniently skipped. Use the --revision
option to specify a target revision.
The current revision can be discovered via juju status output (see column ‘Rev’). For the ceph-mon charm:
App Version Status Scale Charm Store Rev OS Notes
ceph-mon 13.2.8 active 3 ceph-mon jujucharms 48 ubuntu
Important
As stated earlier, any kind of upgrade should first be tested in a pre-production environment. OpenStack charm upgrades have been tested for single-step upgrades only (N+1).